At the Bug Light end of the Greenbelt Walkway there's a gravel parking lot with vegetation climbing its fence. Beyond it, a cracked lot runs down to a pier that's fenced off, and the white petroleum tanks loom over both. That's how the Portland Press Herald described the scene in September, in a story about a small group of residents who see a park there.
That lot is the largest idea attached to the Greenbelt this fall. It's also the furthest off. Several other changes are coming to the 5.6-mile path between Wainwright Athletic Complex and Bug Light Park, and they arrive in reverse order of size. A two-week street closure is already underway, while the largest idea still has no budget or date.
The path, and the timetables running beside it
The South Portland Land Trust describes the Greenbelt as a City-managed route with its main access points at Wainwright Fields, Mill Creek Park and Bug Light Park. Between them it winds through Pleasantdale, Broadview Park, Knightville and Ferry Village. It is also part of the Eastern Trail and the East Coast Greenway. Walking the path itself won't change much this fall. The work is happening at its crossings, at its parks and at its far end.
| Change | Where | Status as of October 12, 2026 | Expected timing |
|---|---|---|---|
| Hill Street realignment | Broadway corridor | Closed since October 8 | About two weeks |
| Greenbelt art panels | Mill Creek Park first, then Bug Light Park, per Press Herald | Artist call closed August 31 | Work targeted by early winter 2026 |
| Mill Creek Bridge #0341 replacement | Mill Creek, near Parkside Terrace | Preliminary public meeting held October 7 | Construction anticipated 2028 |
| Historic maritime park concept | Eastern Waterfront near Bug Light | Council resolve considered September 15 | No funding or schedule |
Two weeks: Hill Street
The fastest change is also the least glamorous. South Portland's Broadway Pedestrian Improvements Project began on Thursday, October 8, with the realignment of Hill Street. According to the city's notice, that section closes around the clock for about two weeks. Traffic detours via Lombard Street, and emergency vehicles can pass as needed. If the work holds to its estimate, Hill Street should reopen around the third week of October.
Sebago Technics, the project consultant, describes the work as pedestrian improvements on both the Broadway corridor and the Greenbelt Pathway. The list covers the Hill Street intersection realignment, new crosswalks and sidewalk, drainage and access management, and bus-stop crossings with rectangular rapid flashing beacons. The stated goals are safety, accessibility, transit use and connectivity. Most walkers will feel this at the edges of the path, at the places where the Greenbelt meets traffic.
Some of this corridor is already done. The same consultant lists Broadway sidewalk work from Whitehall Avenue to Lincoln Street, and along Church Street, as a separate project completed in 2025. The Hill Street work is the next piece of that effort.
Early winter: art along the path
The next change to appear will be painted. In late July the city announced a pilot public art project for the Greenbelt. Artists paint wooden panels measuring 4 by 8 feet. Each installation has two surfaces, each artist gets one surface, and the city set aside $5,000 to support the project.
The Press Herald reported in August that four artists would be chosen. It said the first mural would go in Mill Creek Park, the second at Bug Light Park, and that the program would keep growing until there's art along the whole trail. The city's call for artists is more cautious. It lists panel locations as still to be determined and asks that artists be able to finish by early winter 2026. A demonstration surface was set up in Mill Creek Park on August 8.
The bid listing shows the call closed on August 31. The listing doesn't name the selected artists. Under the process in the call, a committee reviews proposals and the City Council votes on final designs, so a council vote is the next public step to watch for.
If the Press Herald's sequence holds, the second panel would go up at Bug Light Park, at the same end of the path as the largest and slowest idea.
2028: the Mill Creek Bridge
The Mill Creek Bridge, number 0341, runs on a much longer timetable. MaineDOT held a preliminary public meeting at City Council Chambers, 25 Cottage Road, on Wednesday, October 7, to discuss replacing it. The city's notice places the bridge over Mill Creek, 0.02 of a mile northwest of Parkside Terrace.
The preliminary schedule in MaineDOT's project story map runs past this fall and the next. Design wraps up across fall 2026 and spring 2027, the job goes out to contractors in fall 2027, and construction is expected in 2028. For anyone around Mill Creek, the October meeting starts a process that will take years. Nothing changes on the ground this season.
No date: a park at Bug Light
At the eastern end, the residents in the Press Herald story want a Liberty Ship Memorial Park at Bug Light. Their goals are to protect the shoreline, prevent development, and create a continuous path between Spring Point and Ferry Village. Bug Light Park already holds the Liberty Ship Memorial and the Portland Breakwater Lighthouse.
The day before that story ran, the City Council took up RESOLVE #3-26/27, sponsored by Councilor West. As drafted, it would express support for publicly accessible shoreline and open space in the Eastern Waterfront Coastal Area, possibly as a historic maritime park. The resolve would welcome a private, resident-led capital campaign to raise money for buying land or easements along the waterfront. It would also direct the City Manager to talk with property owners about future land uses that would move the area away from petroleum-products businesses.
The history in the background section explains why this ground matters. The council agenda notes that 244 Liberty ships and 30 Ocean ships were built at Cushing's Point during World War II. It also records that residents were displaced and homes lost when the shipyard was built. The resolve connects all of this to the city's recently adopted Comprehensive Plan, which calls for connected public access, open space and flood-resilient measures along the Eastern Waterfront.
The City Manager's position paper is explicit about the resolve's limits:
"As drafted, the resolve expresses Council policy support and directs staff engagement, but it does not itself appropriate City funds, acquire property or easements, authorize eminent domain, approve a specific redevelopment proposal, or commit the City to purchase or develop a park."
The same paper acknowledges that private property rights would have to be acquired and that the City's resources are limited. Any purchase, funding or formal commitment would need to come back to the Council separately. Staff recommended approval. Even if adopted, the resolve would leave the most ambitious Greenbelt idea of 2026 depending on a private campaign whose purpose the agenda describes but whose details it doesn't give, and on conversations with property owners whose results aren't settled in advance.
Bug Light Park keeps its usual routine in the meantime. It's open daily from 6 a.m. to 9 p.m., and the restrooms are seasonal.
Where the walk passes through Knightville
The Greenbelt's stretch through Knightville passes close to Ocean Street. These spots appear in recent local coverage or on the businesses' own sites, and hours can change between seasons:
- Cia Cafe, 72 Ocean St. Its own site posts weekly hours, Sunday breakfast hours, and breakfast and lunch menus dated 2026.
- The Send Brewing Co., 15 Ocean St. Its site describes a food-and-beer business in Knightville and lists weekly opening hours.
- The Garden Bar, 173 Ocean St. Portland Food Map reported its opening in July 2025.
- Himalayas on the Bay, 60 Ocean St. Portland Food Map reported in early August 2026 that it planned a limited-menu opening on Friday, August 7.
Later in the season, the city's last Mill Creek Park tree lighting we could find was on Friday, December 5, 2025. The city calendar hadn't listed a 2026 date as of this writing.
What to watch for next
Each change has a next step to watch for. Hill Street should reopen around the third week of October. The art panels need a City Council vote on designs before they can go up by early winter. The bridge goes out to contractors in fall 2027. Under the resolve as drafted, the park concept would rest with a private campaign and with City staff's talks with waterfront property owners, and any purchase or funding would have to come back to the Council as a separate vote.